The Sunyani project is intended to increase capacity, while the Bolgatanga airport would improve air links to northern Ghana.

GHANA – Ghana Airports Company Limited (GACL) plans to begin construction and upgrade work at airports in Wa, Bolgatanga and Sunyani before the end of 2026 to extend air cargo and trade access beyond Accra, according to Managing Director Yvonne Nana Afriyie Opare.
The works include upgrades to existing airports in Wa and Sunyani and construction of a new airport in Bolgatanga.
Cargo infrastructure and regional trade corridors
At Wa Airport, planned improvements include a new terminal and an extension of the existing runway, the latter determining which aircraft types can serve the facility and therefore the freight payload available.
The Sunyani project is intended to increase capacity, while the Bolgatanga airport would improve air links to northern Ghana, a region that produces shea, maize, groundnuts and livestock and currently moves south by road to Accra or exports via neighbouring corridors.
The Tamale expansion, listed as completed in the government’s 2026 budget, includes dedicated cargo operations facilities and infrastructure for Hajj pilgrims.
Tamale sits on the northern trade axis, serving the Savelugu, Yendi and Bolgatanga production zones. Dedicated cargo handling there reduces reliance on Accra for northern exports.
GACL also wants to encourage direct flights between major cities, with potential routes including Kumasi to Tamale, Tamale to Wa, and Sunyani to Kumasi, allowing passengers and belly-hold cargo to travel between regional centres without connecting through Accra.
The company says that more direct regional flights could also facilitate trade, tourism and economic activity outside the capital, thereby reducing the concentration of passenger and freight flows through a single gateway.
Wider programme and cost context
At Accra’s international airport, construction is underway on a concourse linking Terminals 2 and 3, with completion scheduled for November 2027.
Meanwhile, in Kumasi, design work has begun on a new domestic terminal.
The government is working to revive a national airline, with operations planned for 2027. In early November, authorities collaborated with Boeing to develop a launch roadmap.
Moreover, import duties on aircraft spare parts have been eliminated to reduce operating costs and help lower airfares.
Ultimately, Ghana’s airport upgrades will expand northern cargo access only if cold chain and freighter capacity are in place.
Sign up HERE to receive our email newsletters with the latest news and insights from Africa and around the world, and follow us on our WhatsApp channel for updates.