Slaughterhouses, a laboratory, and an agricultural aggregation and services centre are among the planned facilities.

DRC – The Democratic Republic of Congo has signed a US$41 million contract to develop the Ngandajika agro-industrial park in Lomami province, with construction scheduled to begin in January 2027, according to Bruno Miteyo Nyenge, head of the president’s Civil Household.
A Chinese company will carry out the construction work, according to a message reported by the local news outlet 7sur7.cd, although neither the contractor’s identity nor the contractual completion deadlines have been disclosed.
Park infrastructure and land allocation
The contract forms part of the Ngandajika Agro-Industrial Development Support Program, approved in November 2021 with support from the African Development Bank.
According to AfDB procurement documents, the park allocates 159 hectares to livestock farming, 51 hectares to industrial activities and 32 hectares to logistics across the 534-hectare site, with additional areas for training and research, administrative services and shared infrastructure.
The site will feature 47 kilometers of internal roads, including 7.5 kilometers paved, as well as electricity distribution, sanitation, drinking water networks, and waste treatment and storage infrastructure.
In addition, slaughterhouses, a laboratory, and an agricultural aggregation and services centre are among the planned facilities.
Electricity supply includes a hydroelectric power plant on the Lubilanji River at Mpanda Mushilu, with financing to be raised separately.
Private sector participation and transport links
In August 2026, the PRODAN management unit issued a call for expressions of interest to recruit a consulting firm to develop a business plan, financial model, and legal framework.
The assignment includes assessing the private investment required for processing plants, warehouses, and logistics facilities under a public-private partnership, as well as identifying measures to facilitate access for small and medium-sized businesses.
In late February 2026, the government and the AfDB signed a financing agreement worth approximately US$155 million to improve transport connections to the park and the Nkuadi agricultural centre.
On October 12, the AfDB issued an international tender to pave 125 kilometers of road under two contracts, covering the 47-kilometre Lukalaba-Ngandajika road and the 78-kilometre route linking Ngandajika, Nkuadi, and the park, each with an expected 30-month construction period.
The bid deadline was originally set for December 4, 2026, and has been extended to December 18, 2026.
Ultimately, construction begins in January 2027, but the park’s commercial viability depends on PPP investment and 125 kilometres of access roads yet to be tendered.